- Education Institution
HKU Biological Sciences Building
The school occupies an 11-floor building with a wide range of state-of-the-art equipment for experimental biology, biotechnology, food and nutritional science, ecology, systematics, animal behaviour, plant and animal science and other areas of research.
To serve the personnel, environment and sophisticated equipment, delicate E&M works under this contract include the detailed design, supply, installation; T&C of all mechanical is the major challenge of this project.
To attain the designated levels of pressure re respective laboratories.
Precise sequential arrangements re-provision of electricity to each machine.
Detail and precise co-ordination of medical equipment and E&M services and timely logistic control of equipment are the key factors of successful completion of this project.
Client
The University of Hong Kong
Project period
Jan 1998 – Jul 1999
Scope of works
- Extra Low Voltage (ELV) systems
- Fire services
- Low-pressure Towngas distribution system
- Mechanical Ventilation & air-conditioning (MVAC)
- Plumbing & Drainage
- Power distribution system and lighting to various medical laboratory